PWVJer
Joined: 13 Dec 2005 Posts: 946
|
Posted: Wed Jul 15, 2015 2: 26 pm Post subject: Clairton Branch-Bruceton AVR Interchange up-date |
|
|
Clairton Branch, the " Tie Gang" has completed about 90% of their branch work.
Today the crew was finishing-up at the end of the Clairton yard tracks.
Steel ties are now in place on the hard-curve near State Street X-ing at
the NS River connection.
Some CWR installed on the branch curves. The Rail/Surface gang(s)
have more work.
WLE Bruceton Bridge area work. Today, a private contractor was working
on clearing/cleaning the clogged 5' culvert located in the area under the ROW bridge approach, and
near-by Station foundation on the WLE main line.
CWR gang(s) to work the W&LE Main Line Westland to Rook starting next week.
Crews to be housed in the Hotels near Bridgeville Pa.
AVR/Carload Express, North switch(near Whitehall Tunnel/Curry Road bridge)
in place and "cut-in" on the new siding ROW. CWR and tie gangs now have
all ties, rail, spikes, clamps in place, and ROW surface work complete & ready for install.
Maybe, more AVR interchange fracking traffic go'n WLE-East to SWP Everson connection?
Last edited by PWVJer on Sat Jul 18, 2015 8: 25 am; edited 1 time in total |
|
Back to top |
|
|
pitt1292 photography
Joined: 25 Apr 2015 Posts: 23 Location: Pittsburgh, Pa
|
Posted: Thu Jul 16, 2015 8: 08 am Post subject: |
|
|
When I drove the branch last Sunday after fishing I notice on the curves where the CWR was in place that they need to redo most of the rail plates, other than that the tracks look much better now than before, also what is wrong with the bridge exactly? |
|
Back to top |
|
|
PWVJer
Joined: 13 Dec 2005 Posts: 946
|
Posted: Thu Jul 16, 2015 10: 27 am Post subject: ...bridge & branch work |
|
|
The Ravensburg tunnel & small stream bridge(s) at the mouth of the
Clairton Yard are now fine. Fans can get a nice safe view of those stamp-formed-steel-ties
from the parking lot at the State-street X-ing.
Last edited by PWVJer on Sat Jul 18, 2015 8: 27 am; edited 1 time in total |
|
Back to top |
|
|
pitt1292 photography
Joined: 25 Apr 2015 Posts: 23 Location: Pittsburgh, Pa
|
Posted: Thu Jul 16, 2015 2: 13 pm Post subject: |
|
|
Ok, from what I heard from a few sources is that they can run any work trains. So I would assume work will start soon? But I will do some asking around to find out. |
|
Back to top |
|
|
Rich_S
Joined: 23 Aug 2011 Posts: 253 Location: Baden, PA
|
Posted: Sat Aug 15, 2015 5: 12 pm Post subject: |
|
|
Any news on the branch?
Is the rehab work done?
Are they running coke trains on the branch? _________________ Regards,
Rich S. |
|
Back to top |
|
|
PWVJer
Joined: 13 Dec 2005 Posts: 946
|
Posted: Sun Aug 16, 2015 8: 30 am Post subject: ...branch work |
|
|
Rich & others, as of 8/9/15....
Entire branch & yard have new ties/switch's installed. Some ROW sections have S.H.- CWR installed.
Additional s.h. stick & cwr yet
delivered & installed. Peters Creek Bridge, contractor cleared
all brush/trees around structure. Initial equipment access road/contractor
initial survey work may be completed. No regular traffic movements yet.
(shot a bunch of images)
AVR Bruceton Interchange as of 8/9/15.
All new CWR installed on main Whitehall Tunnel to/thru Bruceton Interchange.
The two small bridges have been rebuilt. Heavy CWR, Ties-spikes-Plates-clamps staged on main/new siding ROW.
Main complete groomed ballast/tamped/re-ditched. Siding project may be completed as of this post?
No info on AVR rail traffic, will try to visit & take pics next week.
JR/JZ |
|